Tuesday, May 12, 2026

GCE A/L ICT Unit 7 - System Analysis & Design Exam Questions and Answers

GCE A/L ICT Unit 7 - System Analysis & Design

GCE A/L ICT Unit 7 - System Analysis & Design

Unit 7: System Analysis & Design is one of the most important units in GCE A/L ICT (Sri Lanka Local Syllabus). It is heavily tested in MCQ, structured, and essay questions.

1. Information Systems

Definition: An Information System is a collection of people, hardware, software, procedures, and data that work together to process data into meaningful information.

Key Idea

Input → Processing → Output (Information)

2. System Development Life Cycle (SDLC)

SDLC is a structured process used to develop information systems efficiently.

  1. Planning
  2. Feasibility Study
  3. System Analysis
  4. System Design
  5. Development
  6. Testing
  7. Implementation
  8. Maintenance

3. Feasibility Study

  • Technical: Technology availability
  • Economic: Cost vs benefit
  • Operational: User ability
  • Legal: Law compliance
  • Schedule: Time management

4. Fact Finding Techniques

  • Interviews
  • Questionnaires
  • Observation
  • Document Study

5. Data Flow Diagram (DFD)

A Data Flow Diagram (DFD) is a graphical representation of how data moves through a system.

DFD Symbols

  • Circle → Process
  • Arrow → Data Flow
  • Rectangle → External Entity
  • Open Rectangle → Data Store

6. DFD Past Paper Questions (Very Important)

Question 1

Q: Draw a Context Diagram for a Library Management System.

Answer: A single process representing the whole system connected to external entities like Student and Librarian.

Explanation:

A context diagram is the highest level DFD showing system boundaries and external interactions only.


Question 2

Q: Draw Level 0 DFD for a School Admission System.

Answer: Includes processes like Receive Application, Process Application, and Generate Admission Result.

Explanation:

Level 0 DFD breaks the system into main processes and shows data flow between them.


Question 3

Q: Identify symbols used in DFD.

Answer:

  • Process → Circle
  • Data Flow → Arrow
  • External Entity → Rectangle
  • Data Store → Open Rectangle

Question 4

Q: Differentiate Context Diagram and Level 0 DFD.

Context DiagramLevel 0 DFD
Shows whole system as one process Breaks system into sub processes
No internal processes shown Internal processes shown

7. System Testing

  • Unit Testing
  • Integration Testing
  • System Testing
  • Acceptance Testing

8. System Conversion Methods

  • Direct Changeover
  • Parallel Running
  • Pilot Running
  • Phased Implementation

9. Maintenance Types

  • Corrective Maintenance
  • Adaptive Maintenance
  • Perfective Maintenance

Exam Focus Areas

  • SDLC (Very Important)
  • DFD Drawing (Most Repeated)
  • Feasibility Study
  • Testing Methods
  • Conversion Methods

Exam Tips

  • Practice DFD drawing daily
  • Memorize SDLC stages
  • Focus on past paper patterns

GCE A/L ICT Unit 7 - System Analysis & Design (Sri Lanka Local Syllabus)

No comments:

Post a Comment